The housing company’s window project is progressing towards implementation. The model installation of new windows was successfully carried out in apartment E37 in February. The long-prepared window renovation begins in Yläkello in early April, and the estimated duration of the renovation is about six months.
In the window renovation, all windows and balcony doors will be replaced. The windows of common areas will also be replaced. The work is estimated to take 1-2 working days per apartment.
Work will begin in apartments of buildings E and F. After that, buildings G and H will be next, then buildings A to D, and finally building I to K. The contractor, Pihla Oy, will inform residents when window installations for their stairwell are approaching. Subsequently, the specific installation time for each apartment will be announced at least 1-2 days before installation.
For any questions related to the project, residents can contact the contractor’s representative (Christian Söderlund, christian.soderlund@pihla-tiivi.fi / tel. 044 762 8316).
Residents can take a look at the model window in the housing company’s hobby room, which can be accessed through the bike storage of buildings E and F if desired.